| Home > NETT21 > Energy-Saving Technology at Business-Related Buildings > Cases of Newly Constructed Buildings | |
First Headquarters Building of Sanyo Electric Co., Ltd.
1. Overview
![]()
(Photo provided by Sanyo Electric Co., Ltd.)
Design concept
- Strategic information base for Sanyo Electric Group
- Reduction in total construction cost
- Energy conservation; low running cost
- Comfortable and convenient office
- Building friendly to global environment
- Building in harmony with surrounding environment
- Building data
Location 2-5-5 Keihan-hon-dori, Moriguchi Owner Sanyo Electric Co., Ltd. Completion date October 2000 Architectural design Nikken Sekkei Co., Ltd. Equipment design Nikken Sekkei Co., Ltd. Contractor (building) Joint venture of Ohbayashi Corp., Zenitaka Corp., Konoike Construction Co., Ltd. and Nakamichi Corp. Contractor (air-conditioning) Joint venture of DAI-DAN Co., Ltd. and Toyo Thermal Engineering Co., Ltd. Contractor (sanitation) Joint venture of DAI-DAN Co., Ltd. and Toyo Thermal Engineering Co., Ltd. Contractor (electrical) Joint venture of Kinden Corp., Sumitomo Densetsu Co., Ltd. and Chuo Densetsu Co., Ltd. Number of floors (above ground) 10F Number of floors (below ground) 1F Height 45.55m Structure S,SRC RC Site area 8,703.48m2 Building area 3,652.41m2 Total floor area 29,634.86m2 Standard floor area 2,669.11m2 Air-conditioned area - Use1 Office 100% ![]()
(Sources provided by Sanyo Electric Co., Ltd.)
2. Energy-Saving Measures Adopted
Architectural planning
Adoption of IR reflecting glass for heat load reductionBuilding equipment and operation planning1. Adoption of cogeneration system (for emergency power generation as well)
2. Adoption of photovoltaic power generation
3. Adoption of Sanyo's active solar system "Solight"
4. Adoption of ice thermal storage heat pump air-conditioning
PAL/CEC
PAL 79Mcal/m2 CEC/AC 1.13 CEC/V 1.09 CEC/L 0.68 CEC/EV 0.14 ![]()
(Sources provided by Sanyo Electric Co., Ltd.)